Early completion of Rehabilitation/Reconstruction of Damaged Paved National Road

September 29th, 2011 by Filipino | No Comments | Filed in The News

OIC District Engineer Sandy T. Pua of DPWH Northern Samar First Engineering District express delight over the early completion of the Rehabilitation/Reconstruction of Damaged Paved National Road along Catarman-Laoang Road.

According to Pua, this project which was completed on August 31, 2011 was the largest by cost and coverage for 2011, with a budget amounting to P28,450,000.00.

The work covered asphalt overlay with an area of 10,511 square meters, sealing of pavement cracks and joints, reblocking of 45 blocks, reflective thermoplastic pavement markings from Km. 744+077.50 to Km. 745+116.10, and replacement of 1 approach slab at Taguibian Bridge.